US Embassy Compound Temporary Housing - Islamabad, Pakistan
Project Name
US Embassy Compound Temporary Housing - Islamabad, Pakistan
Contract No.
SALMEC-09-C-0008
Project Owner
U.S. Department of State
Type of Project
Fixed Price / Design-Build
Completion Date
NTP: 5 February 2009
Completion: 5 June 2009
Extended with Phase 2: 20 July 2010
Completion: 5 June 2009
Extended with Phase 2: 20 July 2010
Contract Value
$31,801,464 Total Current
Duration
4 Months after NTP (Phase 1)
Offeror's Role
Framaco International: Leader of Prime Contractor, FEM JV
Work Performed by the Offeror
Framaco: 100% (As the leader of the Joint Venture)
Relevance to Subject Contract
- Design-Build OBO Contract
- Temporary Housing and Supporting Facilities Works
- High Security Requirements